born2drill
Geotechnical
- Feb 23, 2005
- 80
I'm dealing with a situation on a DOT project where the State does not want to accept several anchors due to differences between the jack calibration and load cell readings. There are significant descrepancies - the load cell showing as little as only 65% of the test load in the worst case.
These are large (260kip - 375kip) strand anchors supporting a sheetpile wall, performance tested to 150% DL with a 10-minute creep hold. All were tested with the same jack and load cell on the same day. The tests met the criteria for elongation (above PTI min elongation) and creep (under 0.040" in 10 minutes).
Of course, the DOT is taking the load cell readings as gospel and recommends retesting the anchors unless I can provide an adequate explanation for the differences.
Does anyone have any experience with this situation? I'd appreciate any suggestions.
These are large (260kip - 375kip) strand anchors supporting a sheetpile wall, performance tested to 150% DL with a 10-minute creep hold. All were tested with the same jack and load cell on the same day. The tests met the criteria for elongation (above PTI min elongation) and creep (under 0.040" in 10 minutes).
Of course, the DOT is taking the load cell readings as gospel and recommends retesting the anchors unless I can provide an adequate explanation for the differences.
Does anyone have any experience with this situation? I'd appreciate any suggestions.