Geotechnical76
Civil/Environmental
- Aug 22, 2003
- 36
We are designing a wall with sheetpiles and tiebacks (anchored at both ends to sheetpiles). Another feature that is added to the site will be a new concrete bleacher with the bottom of footings about 4 feet from the ground surface. The anchors in the original design are placed about 2 feet from the ground surface. My question is how can we protect the tiebacks from sagging? Loads from these concrete blocks above the tiebacks will add additional stresses. One option is to use rock anchors by installing the tiebacks without sheetpiles at the other end and grout them in rock or soil. The other option is to use a concrete conduit and run the tiebacks through them. The first option will be expensive, while the second one will be cheaper. Does anyone have expereince with such siituations? How to calculate the additional stresses in the tiebacks? Any practical problems from usning the concrete conduits?
Thanks
Thanks