facca
Civil/Environmental
- Mar 27, 2004
- 37
I am a bridge contactor hired by a highway agency to construct a semiintregal abutment structure designed by the highway agencies consultant.This abutment is supported on caissons founded on rock and tied back with a proprietary system.Caissons are already installed and the next phase of the project well involve installing the tie back wall and then constructing abutment and anchoring it to the tie back wall.The contract stated the our supplier was to provide a statement of satisfactory internal & external stability.Our suppliers goetech firm statement was as follows the design of the 2h:1v cut slopes were found to have insufficient stability based on parameters provided in the soil report and it is not possible to achieve adequate global stability with any structure associated with this slope.My problem is that I am being told that it is my responsiblity to provide adequate global stability. I am only a contractor not a designer.Any insights would be helpful.