Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Tier 5 Health Care Power System

Status
Not open for further replies.

Mbrooke

Electrical
Nov 12, 2012
2,546
Anyone know how to economically design a system such that each critical area has multiple independent power feeds?

Basically what data centers do but without all the UPSs.


image_22258_cz72yv.jpg
 
Replies continue below

Recommended for you

I don't understand the "Break before make" and "Make before break" on the tie breakers.

Bill
--------------------
"Why not the best?"
Jimmy Carter
 
I think it means you open the sub-main first before closing the tie; close the submain before opening the tie downward respectively.

But in any case the pic is an example for discussion purposes.

Have at least 3x replication for ICUs, ORs, ect.
 
Thanks.
I thought it was something like that.
Better to ask than to guess which was to be opened first.
There may be some faint lines showing interlocks that are not coming through on my monitor.

Bill
--------------------
"Why not the best?"
Jimmy Carter
 
Sync check needed between the various UPS distribution. Definitely a challenge economically...

Mike
 
There probably won't be any major UPSs, just the structure of having 3 independent power sources in each critical area.


Regarding economics- I'm guessing the fact only critical loads will transfer between these three branches means basically 3 smaller systems equal in capacity to one large system?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor