Good day,
2 questions please :
what is the maximum time allowed between excavating and concreting a bored pile without affecting pile integrity ?Is 24 hours ok ? I couldnt find anything in the specs.
2- if a bored pile is concreted, can we begin directly excavating the adjacent pile which is 3x diameter far ?
Thank yiu
2 questions please :
what is the maximum time allowed between excavating and concreting a bored pile without affecting pile integrity ?Is 24 hours ok ? I couldnt find anything in the specs.
2- if a bored pile is concreted, can we begin directly excavating the adjacent pile which is 3x diameter far ?
Thank yiu