ReliabilityPF
Electrical
At our plant we have several generators running in parallel at 50HZ, there is a speed trip for the prime movers at 47Hz, is it recommended to put a time delay for this trip so the system can recover from an electrical upset. We have a load shedding system witch the last step is 47.5hz.