gadwall
Civil/Environmental
- Aug 8, 2006
- 10
I am working on a residential development approximately 35-acres in size. The property is extremly flat( less than 0.2% grade from fron to back.) There was a drainage way on the property that has been relocated. I requested a copy of the drainage calcs for the relocation project and the Town Engineer said there were no calcs. (I thought this was strange). Anyway, I performed my own analysis of the overall basin using HydroCAD. I looked at the 10-yr and 100-yr storm events.
When I submitted my report to the Town, the Town Engineer said that it was to information to digest and that he really only needed a report on my development. I disagree. The Development will be directly influenced by the flow in the drainage way. The WSE must be known to apply tailwater conditions to the model.
The drainage way enters my site by a double 6x6 box culvert. The original channel was very iregular in section. It was approximately 3 feet wide at the bottom and about 4 feet deep. The relocated channel is 6 feet wide at the bottom, 4 feet deep, with 3:1 side slopes. Historically there have been no reports of flooding in this area. The HydroCAD model showed the average depth of flow in the channel to be 2.72 feet and 3.78 feet for the 10-yr and 100-yr storms, respectively. I do not believe this to be representative of the situation.
So, here is my major issue. The time of concetration for the development will be on the average of 5-10 minutes. The off site areas have times of concentration in the 30-90 minute range. When the calculations are performed, there seems to be a reduction of runoff. This scenario may be true for a storm of short duration. The runoff from the site will reach the drainage way well ahead of the off site runoff. What happens when a longer duration storm occurs? How do I model this scenario? The Town engineer is trying to push on-site detention, but I am not sure that it is really needed. Any suggestions?
Oh yeah, the model seems to be plagued with [80] Warning messages. I have tried changing the finer routing control to no avail. I think that because the area is so flat that the tailwater is causing a reverse flow condition. How do I model this?
When I submitted my report to the Town, the Town Engineer said that it was to information to digest and that he really only needed a report on my development. I disagree. The Development will be directly influenced by the flow in the drainage way. The WSE must be known to apply tailwater conditions to the model.
The drainage way enters my site by a double 6x6 box culvert. The original channel was very iregular in section. It was approximately 3 feet wide at the bottom and about 4 feet deep. The relocated channel is 6 feet wide at the bottom, 4 feet deep, with 3:1 side slopes. Historically there have been no reports of flooding in this area. The HydroCAD model showed the average depth of flow in the channel to be 2.72 feet and 3.78 feet for the 10-yr and 100-yr storms, respectively. I do not believe this to be representative of the situation.
So, here is my major issue. The time of concetration for the development will be on the average of 5-10 minutes. The off site areas have times of concentration in the 30-90 minute range. When the calculations are performed, there seems to be a reduction of runoff. This scenario may be true for a storm of short duration. The runoff from the site will reach the drainage way well ahead of the off site runoff. What happens when a longer duration storm occurs? How do I model this scenario? The Town engineer is trying to push on-site detention, but I am not sure that it is really needed. Any suggestions?
Oh yeah, the model seems to be plagued with [80] Warning messages. I have tried changing the finer routing control to no avail. I think that because the area is so flat that the tailwater is causing a reverse flow condition. How do I model this?