l3oertjie
Mechanical
- Nov 14, 2007
- 4
Is it possible to dry out a 300mm thick 30MPa concrete slab with a 25mm polystyrene layer and 75mm screed on top already in position? Area under question - approximately 70m^2. Being an HVAC specialist, the engineer asked me - all I can think of is to de-humidify and heat the air below the slab - apparently this is not an option and work has to be done from above..... Any suggestions?