geo321
Civil/Environmental
- May 17, 2015
- 85
Hello,
I have 2 independent questions
1- For a cantilever beam where the top reinforcement can not be anchored in the column since the ldh (ACI318-08) is bigger than the columns dimensions, is it ok if i extend the top reinforcement into the adjacent slab and make a class A splice ? (refer to the attached section). (PS i dont want to decrease the bars diameter and increase their numbers)
2- An existing reinforced concrete solid slab needs to be enlarged. Dowels will be planted in the slab. A hole of 15 x bar diameter will be drilled and bar along a bonding agent will take place. The connection between the existing and the new slab is a pinned connection. Correct?
If i need to have a continuity and a moment connection, i should demolish a part of a slab and ensure that the bars have the adequate development length. Correct?
Thank you all
I have 2 independent questions
1- For a cantilever beam where the top reinforcement can not be anchored in the column since the ldh (ACI318-08) is bigger than the columns dimensions, is it ok if i extend the top reinforcement into the adjacent slab and make a class A splice ? (refer to the attached section). (PS i dont want to decrease the bars diameter and increase their numbers)
2- An existing reinforced concrete solid slab needs to be enlarged. Dowels will be planted in the slab. A hole of 15 x bar diameter will be drilled and bar along a bonding agent will take place. The connection between the existing and the new slab is a pinned connection. Correct?
If i need to have a continuity and a moment connection, i should demolish a part of a slab and ensure that the bars have the adequate development length. Correct?
Thank you all