crcivil
Civil/Environmental
- Jan 22, 2012
- 92
In this method, intermittent/alternate permanent reinforced concrete panels are placed in a down-ward process as the excavation continues, and new elements of typycal size 3 m x 3 m are installed employing one prestressed temporary anchor per panel, and constructing a stripe foundation beneath the wall at final excavation level. This means we dig all the way down and start building back up the floor slabs at each level, at which point the anchors are not longer needed since the loads are transfered to the floor slabs/beams.