claytill
Geotechnical
- Jun 13, 2005
- 10
I am currently designing a sludge pond that will require cleanout ~every 2 to 3 years. A trafficable surface is required to support cleanout equipment and our design consists of roller compacted concrete (150 mm), underlain by 3/4" crushed road gravel (200 mm thick),which is underlain by a 32 oz non-woven geotextile (liner protection) follwed by a double 60 mil HDPE liner.
My concern/uncertainty is that during the construction phase the 200 mm of gravel a) may compromise the primary liner during placement of the roller compacted concrete (ie, loaded trucks with RCC), b), 200 mm of gravel maybe insufficient thickness and should be increased, and/or c) maybe a sand layer is required to provide additional liner protection? If anyone has experience with such applications, I would appreciate your comments. Also, any references you could point me to would be great.
My concern/uncertainty is that during the construction phase the 200 mm of gravel a) may compromise the primary liner during placement of the roller compacted concrete (ie, loaded trucks with RCC), b), 200 mm of gravel maybe insufficient thickness and should be increased, and/or c) maybe a sand layer is required to provide additional liner protection? If anyone has experience with such applications, I would appreciate your comments. Also, any references you could point me to would be great.