AlwaysLearnin
Electrical
- Jul 2, 2015
- 5
Good Day. I am working on a project in a facility where the owners have several loads they have deemed "vital" to operations and cannot be in an outage for a prolonged period of time.
Our specific task in this project is the replacement of the upstream distribution equipment including transformers and Switchgear. We are fortunate enough where we can install the new equipment without impacting the existing equipment until the loads are ready for transferring. It is at that phase of the project that several members of my team come into conflict and I am looking for opinions from those more experienced then myself in matters of construction.
The majority opinion on how to rectify this is to install a temporary Motor Control Center and transfer the vital loads over to this temporary unit. The existing Motor Control Center can then be transferred to the new distribution network at leisure. Once the motor control center is transferred, the vital loads can be relocated back to that existing Motor Control Center and the temporary unit demolished. I have seen this method used on equipment were outages were be prolonged due to other schedule incompatibilities or construction phasing requirements.
The minority opinion disagrees with this approach on this particular project. As a disclaimer, I fall into the minority opinion on this matter. I feel that it would be quicker and require less outages of the vital equipment to simply transfer the entire MCC upfront and without construction phasing. I do not feel that the labor time associated with the disconnection and re-connection of a new feeder for an MCC would substantially exceed what is required to transfer the smaller compartments to the temporary unit. For arguments sake consider the MCC feeder to be 6-1/C 500 with ground. The greater portion of the raceway run and cable pull can be done prior to de-energization, leaving only the last few feet of cable dropping into the motor control center and of course making the final terminations.
Am I underestimating the effort required in re-feeding an MCC as compared to the temporary power scheme my peers have suggested?
Thank you for any assistance you can provide.
Our specific task in this project is the replacement of the upstream distribution equipment including transformers and Switchgear. We are fortunate enough where we can install the new equipment without impacting the existing equipment until the loads are ready for transferring. It is at that phase of the project that several members of my team come into conflict and I am looking for opinions from those more experienced then myself in matters of construction.
The majority opinion on how to rectify this is to install a temporary Motor Control Center and transfer the vital loads over to this temporary unit. The existing Motor Control Center can then be transferred to the new distribution network at leisure. Once the motor control center is transferred, the vital loads can be relocated back to that existing Motor Control Center and the temporary unit demolished. I have seen this method used on equipment were outages were be prolonged due to other schedule incompatibilities or construction phasing requirements.
The minority opinion disagrees with this approach on this particular project. As a disclaimer, I fall into the minority opinion on this matter. I feel that it would be quicker and require less outages of the vital equipment to simply transfer the entire MCC upfront and without construction phasing. I do not feel that the labor time associated with the disconnection and re-connection of a new feeder for an MCC would substantially exceed what is required to transfer the smaller compartments to the temporary unit. For arguments sake consider the MCC feeder to be 6-1/C 500 with ground. The greater portion of the raceway run and cable pull can be done prior to de-energization, leaving only the last few feet of cable dropping into the motor control center and of course making the final terminations.
Am I underestimating the effort required in re-feeding an MCC as compared to the temporary power scheme my peers have suggested?
Thank you for any assistance you can provide.