power2020
Electrical
- Aug 18, 2005
- 127
Dear Folks,
In our Project, we have 3.3kv substation, getting supply from Grid and a stand by DG set 3.3kv, 2MW, which is connected to this 3.3KV switchgear for emergency loads.
We have Two distibution transformers (3.3/0.4KV )connected to this 3.3kv switchgear and feeding to 400v Switchgears. These two transformers are DYN1 and solidly grounded.
Can somebody discuss pros and cons of this system?
1) Transformers (3.3kv/0.4kv, DYN1) are solidly earthed.
2) stand by generator (3.3kv 2MW) is RESISTANCE EARTHING NGR.
We are not planning for parallel operation.
What are we need to take care (relay coordination etc.) for GRID & Generator operation?
Thanks in advance..
In our Project, we have 3.3kv substation, getting supply from Grid and a stand by DG set 3.3kv, 2MW, which is connected to this 3.3KV switchgear for emergency loads.
We have Two distibution transformers (3.3/0.4KV )connected to this 3.3kv switchgear and feeding to 400v Switchgears. These two transformers are DYN1 and solidly grounded.
Can somebody discuss pros and cons of this system?
1) Transformers (3.3kv/0.4kv, DYN1) are solidly earthed.
2) stand by generator (3.3kv 2MW) is RESISTANCE EARTHING NGR.
We are not planning for parallel operation.
What are we need to take care (relay coordination etc.) for GRID & Generator operation?
Thanks in advance..