ctnie
Electrical
- Aug 1, 2005
- 4
I am currently working within the wind farm sector (which is a new area for me and my company) can anyone help with the following problem;
Our companies normal arrangement for the connection of wind farm generators to a utilities network is via a daisy change set-up (ie Transformers 33/.690kV, 1.5MVA linked together with 33kv cables on one continuous circuit without 33kv RMU’s.). This form of connection has caused a problem at one site; when the transformers are energised the inrush current from the string of transformers causes a voltage dip on the utilities network that is outside their licence standard.
Is there any other solution to this problem other that fitting 33kv RMU’s at each transformer, along with a supervisory control scheme that allows each transformer to be energised individually? This would no doubt solve the problem but won’t help the bank balance.
Our companies normal arrangement for the connection of wind farm generators to a utilities network is via a daisy change set-up (ie Transformers 33/.690kV, 1.5MVA linked together with 33kv cables on one continuous circuit without 33kv RMU’s.). This form of connection has caused a problem at one site; when the transformers are energised the inrush current from the string of transformers causes a voltage dip on the utilities network that is outside their licence standard.
Is there any other solution to this problem other that fitting 33kv RMU’s at each transformer, along with a supervisory control scheme that allows each transformer to be energised individually? This would no doubt solve the problem but won’t help the bank balance.