Hi,
I was wondering if anyone has experience in concreting by tremie method. Weve been advised to use this in a location for piled foundations, if groundwater is encountered.
Weve decided to use tremie regardless. Would there going to be any issues with using tremie if ground water is not encountered?
Apparently high slummp of around 200mm is recommended with tremie, could this cause an issue?
Thanks
I was wondering if anyone has experience in concreting by tremie method. Weve been advised to use this in a location for piled foundations, if groundwater is encountered.
Weve decided to use tremie regardless. Would there going to be any issues with using tremie if ground water is not encountered?
Apparently high slummp of around 200mm is recommended with tremie, could this cause an issue?
Thanks