DRG76
Mechanical
- May 9, 2007
- 4
I have question related to tributary area and concentrated loads. If you have a concentrated rooftop load on a metal building, AC unit for example, positioned between two intermediate frames how do you allocate that load to each frame? Do you use a ratio of the distance from each frame? Or if it falls within the tributary area for one frame do you assign the whole concentrated load to that frame?