Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SDETERS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Tripping of Centrifugal Compressor on high vibration of NDE Bearing 1

Status
Not open for further replies.

SAB262015

Mechanical
Feb 5, 2022
2
Dear All;

We need urgent help in form of vibration analysis and diagnostics of a very production critical multistage centrifugal compressor, driven by a steam turbine with speed increasing gearbox in between. The gas handled by the compressor is carbon dioxide which is first compressed in low pressure casing and then in this high pressure casing. The layout of the complete compressor train is attached as Annexure-I.

The overhauling of this compressor casing was performed to address the issue of high acid number of lubrication oil due to expected ingress of gas as result of high end seal losses. In this overhauling, rotor was reused along with existing stage separation seal (Material; Stainless Steel). Inter-stage (Material; Aluminum), end seal (Material; Aluminum) and bearings were replaced with new ones. Bearing clearance was set 0.11 mm (90 x 31 mm: LOP). The operating speed of the compressor is 13200-13800 with 1st critical speed as 7700-9800 rpm. Rotor total lenghth:1401 mm and bearing span is 1027 mm The cross-sectional drawing of the compressor is attached as Annexure-I.

On 18th Jan, 2022 during start-up, the compressor tripped twice on high vibration of NDE radial bearing VT-205B and it touched 108 microns. Vibration on all other probes also increased but remained less than alarm (75 micron) and danger limit (100 micron). After internal discussion, it was decided to go a 2nd attempt by lowering the trip limit to 80 microns and reducing time delay from 01 second to 03 second. The compressor tripped in the same fashion and at this point, it was decided to perform detailed internal inspection Vibration signatures of both these tripping is available in form of M/s. Baker Hughes System-1 are attached as Annexure-II.

On dismantling the compressor bundle, the following two salient observations were noted;
1. Rub between rotor (nearly 30% circumference) and stator (Inter-Stage and stage separation seal). All inter-stage seals are of aluminum and stage separation seal is of stainless steel with integral teeth and inter-locking configuration. The same is shown in pictures.
2. Liquid accumulation in sealing gas piping, vent piping as well as in compressor internals.
3. The observations of both overhauling’s are attached as Annexure-III.

Our findings for System-1 vibration signatures is;
a. Referring Bode plot of 1st tripping, there was significance difference between ramp-up and coast down in form of direct vibration, 1X and phase angle. At the same speed of the shaft, this difference is more than 80 microns in VT-205B and it kept decreasing during the coast down.
b. Referring the same bode plot of 1st tripping, there was a speed variation of more than 1000 rpm in less than 10 seconds and it repeated in nearly 2.5 cycles before tripping.
c. During 2nd tripping, the ramp-up vibration again matched the ramp-up of 1st tripping by showing that rotor was exposed to temporary unbalance during the 1st The rotor responded with significant phase change (more than 90°) at VT-205B during the critical speed range of 7700 - 9800 rpm whereas no such behaviors exist in 1st tripping. After a few minutes, the vibration of compressor again increased with phase change but reverted back and finally it tripped on high vibration of VT-205B of 80 microns.
d. In both these tripping, we were in loading phase of the compressor where recycle valve was being closed and compressor was being pressurized to meet the system requirement.

Your expert opinion is requested for the following queries;
I. What are possible causes of both these tripping events?
II. Is the liquid accumulation in a centrifugal compressor can cause temporary unbalance and sudden speed variation as observed in 1st tripping?
III. If thermal bow generated by rub is the cause of high vibration, what is the plausible explanation for source of rub?
IV. Are there any symptoms of mechanical fit-up issue being present in the vibration signatures?

Attachments:
1. Machine Layout and Drawing as Annexure-I.
2. System-1 Vibration signatures as Annexure-II.
3. Observations of 1st and 02nd Overhauling’s as Annexure-III.
4. Gas Condition as Annexure-IV at time of 1st and 2nd tripping and normal full load operation (Before and after shutdown)
 
 https://files.engineering.com/getfile.aspx?folder=614591c3-9669-4927-80f8-dc11cc9014d1&file=Attachment.rar
Replies continue below

Recommended for you

My computer doesnt open these files, but nevertheless, agreed, there should be no liquids in seal gas piping. What is your seal gas medium ? - obviously, current seal gas medium has high dewpoint. Is this seal gas dewpoint conditioned ?
If the compressor casing has liquid accumulation, this should be blown out through automated bottom drains valves operating on-off on a timer sequence. Also check if the suction scrubber demisting element is fouled or if the suction piping to compressor is pocketed.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor