ilan7
Mechanical
- Jun 10, 2003
- 152
Hi to all
We installed a 2 MW turbine and Generator connected to the grid (6.4 KV, 60Hz). While performing a 100% load dump test, the max. Turbine speed was 21% over the normal speed (1,800 rpm). We have certified test reports from the generator and the turbine manufacturers for 130% speed 3 min. tests. Is there any regulation that specify the maximum speed in this case? We talking 2MW, 1,800 rpm Turbo-Gen. set.
We installed a 2 MW turbine and Generator connected to the grid (6.4 KV, 60Hz). While performing a 100% load dump test, the max. Turbine speed was 21% over the normal speed (1,800 rpm). We have certified test reports from the generator and the turbine manufacturers for 130% speed 3 min. tests. Is there any regulation that specify the maximum speed in this case? We talking 2MW, 1,800 rpm Turbo-Gen. set.