patrox777
Structural
- Sep 16, 2004
- 8
On a commercial project, I have a 12 foot tall and around 40 feet long, 12" thick, double matted steel concrete cast in place wall. There is a small 30" wide, 24" deep 'continuous' footing along it's length at the bottom to handle the 'vertical bearing' load.
Once the concrete wall has been poured, one side (the exterior' will recieve backfilling to 10 feet, while the 'inside' will remain at '0' feet and an interior slab will eventually be poured in place. The top of the 'wall' shall recieve precast double 'Tee's' to create a second floor slab.
The current engineered design is for 'in place' loading. Meaning AFTER the precast Tee's are secured to the top to counter the lateral load.
I have been contracted to design 'temporary bracing'for the wall to stablize it while the backfill is being placed and the precast double Tee's are installed on it's top.
Question 1: Besides the typical overturning loads on the wall (which I can assume shall resist nothing to be sure the braces hold)... of what significance is the pressure exerted while compacting the backfill? and are there any other considerations to think about?
Question 2: Any usual bracing for this situation? I was thinking along the lines of adjustable steel pole braces supported on the ground via 4 x 4 x 2feet thick spread footings and attached to the footings and wall with removeable expansion anchors. These braces we use all the time to support concrete tilt-up panels while the 'metal frame and roof structures' are being installed.
Thanks for the help,
Pat.
Once the concrete wall has been poured, one side (the exterior' will recieve backfilling to 10 feet, while the 'inside' will remain at '0' feet and an interior slab will eventually be poured in place. The top of the 'wall' shall recieve precast double 'Tee's' to create a second floor slab.
The current engineered design is for 'in place' loading. Meaning AFTER the precast Tee's are secured to the top to counter the lateral load.
I have been contracted to design 'temporary bracing'for the wall to stablize it while the backfill is being placed and the precast double Tee's are installed on it's top.
Question 1: Besides the typical overturning loads on the wall (which I can assume shall resist nothing to be sure the braces hold)... of what significance is the pressure exerted while compacting the backfill? and are there any other considerations to think about?
Question 2: Any usual bracing for this situation? I was thinking along the lines of adjustable steel pole braces supported on the ground via 4 x 4 x 2feet thick spread footings and attached to the footings and wall with removeable expansion anchors. These braces we use all the time to support concrete tilt-up panels while the 'metal frame and roof structures' are being installed.
Thanks for the help,
Pat.