Hi folks, looking to gather some thoughts.
When a VIII-1 manufacturer receives B16.5 (and B16.47) flanges, what is recorded during receipt inspection, and what type of inspection occurs?
UG-44 requires that B16.5 flanges meet all dimension requirements of B16.5 with the exception of ID. How is this verified, or demonstrated? What objective evidence do you keep on hand to prove you have conducted this inspection?
Of course all markings are recorded. The material spec will be recorded, size, the heat number, mill symbol, etc... But in addition, are all dimensions required per B16.5 recorded? Do you record each dimension, including each bolt hole dimension? Or is it simply assumed that if the markings are acceptable, the flange must meet the dimensional requirements of B16.5 for it's given size and class?
When a VIII-1 manufacturer receives B16.5 (and B16.47) flanges, what is recorded during receipt inspection, and what type of inspection occurs?
UG-44 requires that B16.5 flanges meet all dimension requirements of B16.5 with the exception of ID. How is this verified, or demonstrated? What objective evidence do you keep on hand to prove you have conducted this inspection?
Of course all markings are recorded. The material spec will be recorded, size, the heat number, mill symbol, etc... But in addition, are all dimensions required per B16.5 recorded? Do you record each dimension, including each bolt hole dimension? Or is it simply assumed that if the markings are acceptable, the flange must meet the dimensional requirements of B16.5 for it's given size and class?