Anyone have any recent experience in how long it takes UL to run a 1604 investigation/certification?
The customer service rep quoted 20 WEEKS!!, but she also said that if we have a shorter requirement, the project planner may be able to work with us. Our company has done 1604 cert. once in the past, and it took 7 weeks.
As you may have experienced, I can't talk to a UL planner or engineer until they receive our deposit (1/2 the estimate). I can only talk to customer service, and they don't know anything, but that's another story. In the mean time I need to try to budget time for testing.
The customer service rep quoted 20 WEEKS!!, but she also said that if we have a shorter requirement, the project planner may be able to work with us. Our company has done 1604 cert. once in the past, and it took 7 weeks.
As you may have experienced, I can't talk to a UL planner or engineer until they receive our deposit (1/2 the estimate). I can only talk to customer service, and they don't know anything, but that's another story. In the mean time I need to try to budget time for testing.