Dear all,
A lifting lug or structures will have tensile stress, bending stress and shear stress happening at the same location.
Does Unit Check include shear stress, such that St/Sta + Sb/Sba + Ss/Ssa <=1.0 ?
If no need to include, why ? I think Unit Check is another way to simplify Mohr's Circle, then shear shall be included in the unit check, even it is perpendicular to the other two stresses.
A lifting lug or structures will have tensile stress, bending stress and shear stress happening at the same location.
Does Unit Check include shear stress, such that St/Sta + Sb/Sba + Ss/Ssa <=1.0 ?
If no need to include, why ? I think Unit Check is another way to simplify Mohr's Circle, then shear shall be included in the unit check, even it is perpendicular to the other two stresses.