Unloading from area and loading in another area

Status
Not open for further replies.

soil1999

Geotechnical
Oct 18, 2009
39
We want to move huge amount of soil ( around 2000 cubic m)from over a specific area in a private land and dump those on a different area within the same region. I really appreciate your geotechnical key points/inputs that should be considered in this operation.
 
Replies continue below

Recommended for you

Not much to go on - what do you want to do with it? What ramifications would filling "another area" cause? Soil conditions? Not only from geotechnical point of view - but what about environmental? Any contaminants in the soil you are moving? Etc. 2000 m3 is "not" a huge amount of material. I was once involved with a million m3 in a 800 m stretch of new highway . . . . that was fairly large.
 
BigH I agree that 2,000m3 is not a huge amount - perhaps 200 trucks. I don't think there are many considerations, just get a machine to push the material up an a backhoe to load onto the trucks. Then at the tipping area another machine is needed to move the tipped heaps into the final stockpile.
 