HongKongMick
Civil/Environmental
- Jan 11, 2006
- 3
Hi, I am relatively new to Suretrack and am currently tasked with updating a monthly program. The original program was created on Primavera P3 and imported to suretrack for me to up date.
My understanding is that if I change the data date to the required date and then pres F9 to schedule the project then the project will automatically update and I can then adjust the individual tasks that require adjustment.
However when I schedule the revised program all the tasks are brought forward as id the data date was the new start date and everything is in the critical path as a result. Can anyone tell me what I am doing wrong?
Thanks in advance for any help you can give.
Cheers Mick
My understanding is that if I change the data date to the required date and then pres F9 to schedule the project then the project will automatically update and I can then adjust the individual tasks that require adjustment.
However when I schedule the revised program all the tasks are brought forward as id the data date was the new start date and everything is in the critical path as a result. Can anyone tell me what I am doing wrong?
Thanks in advance for any help you can give.
Cheers Mick