thesilvert
Civil/Environmental
- Oct 22, 2011
- 1
Need some advice from fellow engineers or concreters.
Was pouring concrete for some reinforced footings for a retaining wall when the concrete truck, which has been unloaded and pouring along side the job, ending up in the trench/reo we were working on. The idiot tried to drive out instead of reversing back the way he came in, went too close to the trench, it collapse and he got bogged within the reo. Obviously, we couldn't fix the reo and formwork so the pour was cancelled.
Now, we're left with a half poured footing, with the end (the last point of pour) only halfway to the finished level with reo still exposed. I don't want a cold joint since it is load bearing and I don't exactly want to waste more time, man power and hiring an hammer/excavator and rip out what we've already done and redo the whole thing.
Any suggestions or even better, solutions?
Was pouring concrete for some reinforced footings for a retaining wall when the concrete truck, which has been unloaded and pouring along side the job, ending up in the trench/reo we were working on. The idiot tried to drive out instead of reversing back the way he came in, went too close to the trench, it collapse and he got bogged within the reo. Obviously, we couldn't fix the reo and formwork so the pour was cancelled.
Now, we're left with a half poured footing, with the end (the last point of pour) only halfway to the finished level with reo still exposed. I don't want a cold joint since it is load bearing and I don't exactly want to waste more time, man power and hiring an hammer/excavator and rip out what we've already done and redo the whole thing.
Any suggestions or even better, solutions?