Use of EVM for T&M Contracts

Status
Not open for further replies.

bruehlt

Electrical
Apr 20, 2006
1
I am working with a group that is developing processes and procedures with use of EVM to manage projects within our organization.

The question that is causing concern is - how does one measure performance on a T&M job, since there is no "budget" to work off of?

Any help??
 
Replies continue below

Recommended for you

Come up with the cost equivalent if the work was done out of house.



"Do not worry about your problems with mathematics, I assure you mine are far greater."
Albert Einstein
Have you read FAQ731-376 to make the best use of Eng-Tips Forums?
 
If you are doing T&M work the value is the extended cost of the T&M times the applicable rates and costs. i.e. The value of the T&M is the defacto budget
 
did you specify a "not to excced" cost?

if so, use this as the end point and run the EVM on it.

watch each trend line - work completed vs dolars expended.
 