hidalgoe
Electrical
- Jan 14, 2002
- 42
Our MainSub is fed from two 69kV lines. Each line feeds a 15/20mVA transformer. Each transformer is capable of carring the system load. No primary HV CBs or switchers were used to provide fault interruption with high speed differential relaying. Only primary fuses are being used. Some folks here are suggesting that a breaker and half scheme be used to protect the transformers using a differential scheme with overcurrent relays as a backup, because fuses are not completely adequate. The breaker & 1/2 solution can be very expensive... Please comment.