Hey guys. I am involved in a construction of a boiler in site and soon I am going to start NDT on welded joints . I was thinking to perform RT but due to little access in some cases UT, too. The client´s inspector has told us that the UT technique approved by ASME I is only phased array semi or automatized. I was searching on the ASME I code and I did not find anything related that these techniques are the only approved ones. Someone has some reference of this issue?