Vacuum level required in ASME code during the secondary steelmaking ? 1

Status
Not open for further replies.

stanislasdz

Materials
Jan 20, 2007
250
Is there any level of vacuum required by the ASME code during secondary steelmaking ?

Thanks in advance
 
Replies continue below

Recommended for you

stanislasdz;

No, because this is a process detail step that is not under the scope of ASME B&PV Code.
 
Thanks metenger

Is there any other specifications witch required Vaccum level during secondary steelmalking : API, RCC-M, KTA .....

 
stanislasdz;
Vacuum requirements for secondary steel making, regardless of end use, are between the Purchaser and the supplier.
 
As I understand the rules, the ASME piping code only permits materials that meet the steel-making requirements of ASTM specifications.

I believe that your vacuum requirement is indirectly necessary in order to produce steels to ASTM requirements

Only "fully killed" carbon steels (e.g. ASTM A106 - GrB)are permitted in certain applications.


 