Doing an addition. Existing house has roof trusses. I completed the design while my mind was in stick build mode. There are a couple valleys that I designed as LVLs from the new portion of the house that will break through existing trusses.
Is there a standard connection you guys use? I figured add a vertical chord at the break at a minimum. Sheath off a few feet? I also thought I could run the valley and then stick build back what had to be cut?