I just had a value engineering session on one of my jobs and they came back with a few comments. See below: If anyone has some suggestions on how to respond, I would appreciate it.
1. Eliminate upturned keys in concrete starter walls.
2. Reduce wait time between adjacent concrete placements from 10 days to 3 days.
3. Use steel bar joists and metal decking in lieu of pre-cast concrete planks for roof construction.
4. Do not use hydrophylic expanding rubber waterstops.
5. Use fly ash in concrete.