Based on API 589 closure test requirements, some passing (leakage) is permitted during manufacturer shop closure test.
However what about the passing at construction site during line hydrotest?
Is there any international code or standard for that case?
You know that the test pressure during line hydrotest at site may be lower than that during shop closure test.
Thanks in advance..
Based on API 589 closure test requirements, some passing (leakage) is permitted during manufacturer shop closure test.
However what about the passing at construction site during line hydrotest?
Is there any international code or standard for that case?
You know that the test pressure during line hydrotest at site may be lower than that during shop closure test.
Thanks in advance..