Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Velocity Needed to Purge and Air Lock

Status
Not open for further replies.

Ballintoy

Civil/Environmental
Nov 21, 2004
10
0
0
US
I am trying to develop a general relationship for the velocity needed to purge an air bubble from a water pipe with multiple high spots. Any suggestions?
 
Replies continue below

Recommended for you

The Water Pollution Control Federation Manual of Practice No. FD-4 "Design of Wastewater and Stormwater Pumping Stations" states "A minimum velocity of 1.2 m/s (4 ft/sec) is required in the pipeline to shear the bubble and keep it moving downgrade."

Hope this helps.
 