Dear All,
According to UG-37(g)of BPV Code VIII Div.1, vent holes in reinforcing plates and saddles of nozzles attached to outside of a vessel may be left open or may be plugged when the vessel is in service. My question is what about vent holes in re-pads of supports inside vessels? Any requirement to keep it open or to plug these after welding. What are the implications if left open for the vessels like 3 phase separators?
According to UG-37(g)of BPV Code VIII Div.1, vent holes in reinforcing plates and saddles of nozzles attached to outside of a vessel may be left open or may be plugged when the vessel is in service. My question is what about vent holes in re-pads of supports inside vessels? Any requirement to keep it open or to plug these after welding. What are the implications if left open for the vessels like 3 phase separators?