koodi
Civil/Environmental
- Aug 26, 2002
- 63
A retaining wall will retain soil beneath an existing bridge abutment--i.e. underneath an existing bridge.
1. This will require that the the soil be excavated back to a vertical plane adjacent to the abutment piles.
2. The excavation must not remove soil behind the abutments as this will result in settlement of the the bridge approach.
The soil is sand and gravel. Is there a way to stiffen the soil? What is the best method to excavate back without the soil sloughing out from behind the bridge?...........any thoughts?
1. This will require that the the soil be excavated back to a vertical plane adjacent to the abutment piles.
2. The excavation must not remove soil behind the abutments as this will result in settlement of the the bridge approach.
The soil is sand and gravel. Is there a way to stiffen the soil? What is the best method to excavate back without the soil sloughing out from behind the bridge?...........any thoughts?