jproj
Chemical
- Oct 9, 2001
- 324
I work for a pressure vessel design company and read many technical specifications daily. I have noticed that many companies have conservative specifications.
A few that I have seen include:
1) The use of support rings (vacuum rings) is prohibited.
2) Flux Core Arc Weld is not allowed on pressure parts.
3) Steel manufactured in China shall not be used.
From what I've seen, many of these specifications are the result of an accident (e.g. tank blows up due to shoddy work / material).
My question is: why do companies specify ultra conservative methods of construction? The majority of manufacturers use (and have used) these methods without a problem for decades.
I can see how one would tend to be conservative after an accident, but why not find the root of the cause (e.g. not that the vessel imploded, but the vessel imploded because the vacuum rings were not welded on correctly)? If a weld procedure is to blame, change it. If a certain material composition is needed, verify that you are getting what you are paying for (chemical analysis etc.). I can't understand why someone would buy a 1.5" thick tank instead of a 0.5" thick tank with a couple vacuum support rings.
To me it seams that the price of developing a specification would far out-weigh the additional costs resulting from 100+ over-designed tanks.
Any thoughts?
jproj
A few that I have seen include:
1) The use of support rings (vacuum rings) is prohibited.
2) Flux Core Arc Weld is not allowed on pressure parts.
3) Steel manufactured in China shall not be used.
From what I've seen, many of these specifications are the result of an accident (e.g. tank blows up due to shoddy work / material).
My question is: why do companies specify ultra conservative methods of construction? The majority of manufacturers use (and have used) these methods without a problem for decades.
I can see how one would tend to be conservative after an accident, but why not find the root of the cause (e.g. not that the vessel imploded, but the vessel imploded because the vacuum rings were not welded on correctly)? If a weld procedure is to blame, change it. If a certain material composition is needed, verify that you are getting what you are paying for (chemical analysis etc.). I can't understand why someone would buy a 1.5" thick tank instead of a 0.5" thick tank with a couple vacuum support rings.
To me it seams that the price of developing a specification would far out-weigh the additional costs resulting from 100+ over-designed tanks.
Any thoughts?
jproj