Berko
Civil/Environmental
- Dec 11, 2002
- 45
We are currently faced with a vibrating sewage pump issue & I was wondering if anyone had any ideas as to the problem.
The situation is a an 8M deep wet well sump with a dry well sump interconnected to it via 375mm suction pipework.
Due to the semi-tropical climate, the 2 x 6" (55 kw) wet well submersibles operate (via VSD) upto Approx 260 L/s @ 16M (during dry weather).
Once a storm hits, 1 x 10" vertical, dry well submersible (also on VSD) kicks in upto (530 L/s @ 22M) & the pump station can handle a max duty of 1500 L/s @ 26M (3 pumps in parallel)
Static Head of the system is between 14 & 18M.
The wet well pumps work well on commissioning, however the dry well pumps have a vibration issue. When tested singularly, each pump operated fine upto 40 Hz (Approx. 330 L/s) & then began to vibrate. The vibration got progressively worse as the pumps ramped upto their max. frequency of 50 Hz (vibration reading at 50 Hz = 16mm/sec).
At BWL, the water level is 1.2M above the dry well pumps suction. NPSH A at this point equates to 7M, with the pumps NPSH R value at max duty flow of 550 L/s equating to 5.8M.
All suction pipes are free from blockages & all valves are fully open. Judging by the flow rates being encountered, the pumps are not blocked.
I have ruled out cavitation ??? & think that we may be looking at a Vortexing problem. Although with over 2M of water above the suction pipe inlet this should not occur.
This has got me baffled, if anyone has any suggestions, similar experiences, or advise on solving this issue your input would be appreciated.
The situation is a an 8M deep wet well sump with a dry well sump interconnected to it via 375mm suction pipework.
Due to the semi-tropical climate, the 2 x 6" (55 kw) wet well submersibles operate (via VSD) upto Approx 260 L/s @ 16M (during dry weather).
Once a storm hits, 1 x 10" vertical, dry well submersible (also on VSD) kicks in upto (530 L/s @ 22M) & the pump station can handle a max duty of 1500 L/s @ 26M (3 pumps in parallel)
Static Head of the system is between 14 & 18M.
The wet well pumps work well on commissioning, however the dry well pumps have a vibration issue. When tested singularly, each pump operated fine upto 40 Hz (Approx. 330 L/s) & then began to vibrate. The vibration got progressively worse as the pumps ramped upto their max. frequency of 50 Hz (vibration reading at 50 Hz = 16mm/sec).
At BWL, the water level is 1.2M above the dry well pumps suction. NPSH A at this point equates to 7M, with the pumps NPSH R value at max duty flow of 550 L/s equating to 5.8M.
All suction pipes are free from blockages & all valves are fully open. Judging by the flow rates being encountered, the pumps are not blocked.
I have ruled out cavitation ??? & think that we may be looking at a Vortexing problem. Although with over 2M of water above the suction pipe inlet this should not occur.
This has got me baffled, if anyone has any suggestions, similar experiences, or advise on solving this issue your input would be appreciated.