Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Vibration monitoring due to piles driven near burried pipelines 1

Status
Not open for further replies.

Megas

Materials
Jan 28, 2005
1
Is there any criteria or experience for vibration monitoring of piles driven near burried pipelines? What do we have to watch for? Any minimum frequency expected
 
Replies continue below

Recommended for you

You will be looking for a PPV criterion (Peak Particle Velocity ) I don't believe ther are criteria set as norms or equivalent. You should check with the owner of the pipeline. I recently tendered on a job where the owner of a gaz pipe was setting a limit of 50 mm/s as PPV.
 
Apart from establishing the PPV, you may also consider establishing an action plan for quality control during construction, for example, "at 50%PPV, inform project manager", "at PPV, stop work", etc. This assumes that you have someone monitoring the vibrations during construction. This way, you can avoid problems during construction. By the way, have you considered avoiding driven piles altogether and adopting cast-in-place concrete piles instead?
 
Have a look at "Ground-borne vibrations arising from piling" CIRIA Technical Note 142 isbn 0860173518. There is also a British Steel note "Control of vibration and noise during piling" but I'm afraid I only have a copy of it and no other reference.
 
Look at the Florida Department of Transportation website...they have criteria for structures.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor