Gentlemen,
On a 15 kV ungrounded system,it is normal to use STAR GROUNDED-OPEN DELTA VTs to obtain 59N function.During a ground fault the STAR winding is subjected to full line to line voltage (in the worst case) and continue to operate till the fault is found and cleared. The time taken to clear the fault by the maintenance crew may be 2-3 hours or even 2-3 days especially in remote unmanned subs.
Voltage factor of most VTs are 2xCONT/1.73x60sec. As such, is it possible to buy VTs with a voltage factor of 1.73xCONT to cater for such extended periods of fault clearing? Could anybody please mention about a known manufacturer's web site or contact?
Kiri
On a 15 kV ungrounded system,it is normal to use STAR GROUNDED-OPEN DELTA VTs to obtain 59N function.During a ground fault the STAR winding is subjected to full line to line voltage (in the worst case) and continue to operate till the fault is found and cleared. The time taken to clear the fault by the maintenance crew may be 2-3 hours or even 2-3 days especially in remote unmanned subs.
Voltage factor of most VTs are 2xCONT/1.73x60sec. As such, is it possible to buy VTs with a voltage factor of 1.73xCONT to cater for such extended periods of fault clearing? Could anybody please mention about a known manufacturer's web site or contact?
Kiri