dfranks
Structural
- May 30, 2008
- 11
I understand that in some states they allow MSE designs with a bearing pressure greater than the bearing capacity, IF the contract agrees to build the wall to a height where the pressure and capcity are equal and then wait 30 days. From what I understand the assumed capacity is then increased by the weight of the material that was placed in stage 1 allowing the new overall bearing capacity to accomodate stage 2 or even stage 3 of wall height.
Has anyone else heard of this process?
Does this process make sense, if so why?
Thanks!
Has anyone else heard of this process?
Does this process make sense, if so why?
Thanks!