babak1977
Structural
- May 24, 2015
- 4
we have a 80mx40m aeration tank in a waste water treatment plant, subgrade modulus of the soil is very low, considering structural piles only under tank walls and using FLAC code we obtain the maximum settlement about 700mm at the center of the rectangular tank, safety factor against soil instability is more than 5, and the concrete floor (which is structurally separated from the reservoir walls) thickness is 500mm which acts as a watertightening medium, its stresses are controlled due to its high length to height ratio (high flexibility) and its maximum reinforcement ratio is .02, the only critical issue is whether this big settlement should control the design or not?
note: all connections and pipings are flexible so no limitation is to place on the design due to mechanical and piping issue.
note: all connections and pipings are flexible so no limitation is to place on the design due to mechanical and piping issue.