fadyachkar
Structural
- Nov 11, 2004
- 2
Greetings:
We have a project composed of three basement floors and three upper floors. The basement footprint is larger than the superstructure, which leaves a part of the building with only three basement floors...
Water table level is at Ground Floor Level; i.e. all three basement floors are submerged.
Starting ACI 318-11, H is now specifically stated as being "lateral soil pressure" including water pressure, so we assumed that H accounts for the lateral water pressure and placed thw water uplift on the mat foundation as being F, fluid pressure.
If the water uplift pressure was placed in the combinations as H, then the stability of the whole building is not ensured and piles would be needed even under the footprint of the superstructure, which is not logocal...
Any thoughts
thank you
We have a project composed of three basement floors and three upper floors. The basement footprint is larger than the superstructure, which leaves a part of the building with only three basement floors...
Water table level is at Ground Floor Level; i.e. all three basement floors are submerged.
Starting ACI 318-11, H is now specifically stated as being "lateral soil pressure" including water pressure, so we assumed that H accounts for the lateral water pressure and placed thw water uplift on the mat foundation as being F, fluid pressure.
If the water uplift pressure was placed in the combinations as H, then the stability of the whole building is not ensured and piles would be needed even under the footprint of the superstructure, which is not logocal...
Any thoughts
thank you