bank
Civil/Environmental
- Jan 7, 2003
- 74
The contractor is trying to proofroll the soil on a road construction project. They have discovered that water is migrating into the area from an adjacent undeveloped area. This is preventing the soil from drying sufficiently for them to proofroll.
Geotechnical borings prior to completion of design showed no water in any of the borings. There will be a drainage ditch along the edge of the roadway, but it won't be installed until an outfall structure is constructed. At this time there is nowhere to pump the water to, since adjacent areas are either undeveloped or privately owned by others.
The question arose as to whether or not the ditch can be over-excavated, and some material placed in it to form a temporary barrier until the road and/or outfall system are completed. Does anyone have experience with this or other methods of preventing migrating water from entering a construction area? The affected area is probably no more than 500 feet long.
Geotechnical borings prior to completion of design showed no water in any of the borings. There will be a drainage ditch along the edge of the roadway, but it won't be installed until an outfall structure is constructed. At this time there is nowhere to pump the water to, since adjacent areas are either undeveloped or privately owned by others.
The question arose as to whether or not the ditch can be over-excavated, and some material placed in it to form a temporary barrier until the road and/or outfall system are completed. Does anyone have experience with this or other methods of preventing migrating water from entering a construction area? The affected area is probably no more than 500 feet long.