I am doing a seismic analysis of a bridge in ANSYS workbench. I need to use about 500 sequence steps to get the output history. By default workbench only allows me to give 100 sequence steps. I have RTFM and could not find a way to tweak its setting. If somebody knows please help. Thanks
 
Replies continue below

Recommended for you

Hi,
I never tried to use Workbench for transient simulation, I use sequenced simulation only for little loadsteps. Could it be an idea to specify a timestep instead of a number of substeps? Or, if you don't find your way out in WB, shift to Ansys Classical (where you have none of these kinds of limitations...