tensor1
Mechanical
- Jul 28, 2004
- 3
Our design office tried using MS98 installed on the office network to manage projects in the past. There was 8 project managers each managing 1 to 3 projects and all using a common resource pool of designers. MS98 kept crashing and the system was abandoned. We again want to schedule and track projects but with more capable software. MS98 seems fine for only 1 project in isolation. Should we be looking at web base or the enterprise type software or are we not structuring our projects properly?