Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

weight displacement in muskeg conditions

Status
Not open for further replies.

kengall

Petroleum
Jul 22, 2015
1
We have the job of lifting a pipeline facilities in deep muskeg conditions, the use of cranes is very limited, we have been using airbags to lift ,however the soils up to now have been dense enough to allow us to lift without pushing the skid decks that hold them into the soil. Unfortunately I foresee this as a problem in muskeg condition.
The pipeline is buried and will be dug out, the Valve to be lifted in above ground and it sits in below ground saddles, which need to lowered, this is the reason for lifting.
my question would be , would a fillcrete base for the skid piles be enough to hold the airbags,
Approx 100,000lbs and I have 6, 70 ton air bags to use for lifting,
If there is another solution I am all ears.
 
Replies continue below

Recommended for you

Not to make light (so to speak) of the situation, but I know some muskeg can be pretty rough, and at some point in effect "sky hooks" might eventually be helpful for some phases of such operations? (fyi ).
I have actually seen 48" ductile iron pipes, and even larger and longer steel pipes for penstocks, installed over the years with cargo helicopters in inaccessible slopes and terrain. I will like you however await better answers - have a good weekend!
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor