Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations The Obturator on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Weld Path Strength Calculation for Boilers

Status
Not open for further replies.

pvrerate

Mechanical
Jun 28, 2011
14
A NPS 2, set-on nozzle (Figure PW-16.1(a)) is being installed on a Steam Drum Head. Neither PG-38 nor PG-52 applies. The AI is asking for weld path strength calculations. Such calculations show that the nozzle fails following Figure PW-16.1(a). Is it the Code's intent that these calculations be done even though the nozzle is exempt from reinforcement calculations?

As per PG-32.1.3.1 and PG-32.1.3.1.1, "no calculations need be made to determine the availability of compensation for a single opening not covered by PG-38 or PG-52 in shells, headers, or formed heads whose inside diameter is not less than four times the diameter of the opening and" which is welded, not larger than NPS 2, and attached in accordance with the applicable rules.

Is the preceding sentence or some other area of the Code implying that weld path strength calculations are not required in this instance.

Thanks very much for your advice.
 
Replies continue below

Recommended for you

Yes. Compensation for reinforcement and nozzle load path calculations are two different animals under Section I. Load path calculations show the nozzle weld attachments have been sized correctly to avoid failure in service. Reinforcement calculations pertain to ensuring the shell or head where a hole is placed has not been weakened.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor