Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Weld repairs to A105 Flange

Status
Not open for further replies.

timmckee

Mechanical
Oct 19, 2005
20
Steam leaks on pipe flanges is a common problem at our facility. Often the leaks can only be addressed during an annual maintenance outage. Usually by that time the flange face has been "cut" by the steam.

We have repaired these defects by mechanical removal (grinding, PT the excavation, fill the excavation with weld (SMAW 7018, 300 degree preheat in lieu of PWHT), machine the face to the proper finish (125rms), then PT the face again.

We use jurisdiction approved weld procedures and qualified welders.

Anyone see any problems or deficiencies with this method?

Is the 300 degree preheat necessary? (Sec II states weld repairs are permitted but PWHT is necessary. NBIC allows for 300 deg preheat in lieu of PWHT)

Thanks for your help.

 
Replies continue below

Recommended for you

No problem. Yes, the elevated preheat is required and NBIC Method 1 is a correct application.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor