We are currently building a number of beams that are then obviously proof load tested.
My boss insists on having the lug welds UT (Ultrasonic Tested) prior to proof load test, then MPI (Magnetic Particle Tested) after proof load test.
Other than as a health and safety concern I do not see the point of the test prior to proof load testing, and no-one is allowed near the beams whilst under test anyway.
AS (Australian Standard)4991 Lifting Devices mentions nothing, nor does AS1554 Structural Steel Welding.
Can anyone offer some insight, opinion?