John121
Mechanical
- Jun 23, 2020
- 13
Equipment: Pressure vessel
Thickness: Thickness More than 200mm
Code: ASME section VIII Div 2 and U2 stamp.
As code said that No welding is allowed after Hydrotest.
But piping modeling design progress is far ahead and other hand vendor is worked out the all the possible roller position but there are some cleats on roller path. At progressive design stage we are not prefer relocate the cleats position since it have serious major piping design rework. Also roller position can not changed before hydrotest. Vendor also denied to use RF pad on those clashing cleats since obstruction in rolling path.
So only option balance is that to weld cleats after hydrotest prior to shipment. so it is permissible to weld non pressure attachments on DIV 2 Code stamp vessel after Hydrotest? If permissible then what are the additional requirement.
Also, Any alternative to deal such issue?
Thickness: Thickness More than 200mm
Code: ASME section VIII Div 2 and U2 stamp.
As code said that No welding is allowed after Hydrotest.
But piping modeling design progress is far ahead and other hand vendor is worked out the all the possible roller position but there are some cleats on roller path. At progressive design stage we are not prefer relocate the cleats position since it have serious major piping design rework. Also roller position can not changed before hydrotest. Vendor also denied to use RF pad on those clashing cleats since obstruction in rolling path.
So only option balance is that to weld cleats after hydrotest prior to shipment. so it is permissible to weld non pressure attachments on DIV 2 Code stamp vessel after Hydrotest? If permissible then what are the additional requirement.
Also, Any alternative to deal such issue?